On the eve of Construction Worker Day celebration CEO of “Zaporozhstal” Steel Works Rostyslav Shurma congratulated master builders, working at the Steel Works. At present time more than 1000 people – employees of contractor construction organization: Zaporozhye construction and erection management, Thermoelectrical management, Industrial Union of industrialist of Donbass, Kryvorozhelectromontazh, Donetskmontazhspetsstroy, and other organizations are working at Steel Works.
“As of today, “Zaporozhstal” Steel Works is the largest recruiter for contractor organizations of Zaporozhye, Zaporozhskaya region and neighboring regions. “On the eve of Construction Worker Day, I would like to thank all builders, who in complicated conditions fulfil all required works, to secure the implementation of investment program of Steel Works”, said Rostyslav Shurma, CEO of ”Zaporpozhstal” Steel Works.
Monthly “Zaporozhstal” Steel Works invest more than 100 million UAH into project construction.
At the moment, we complete the project on renovation of blast furnace №4, in rolling mills of “Zaporozhstal” we complete the construction of new hydrochloric acid pickling line, in sintering process we implement the project on construction of gas cleaning of sintering machine №2, it is planned consecutive renovation of gas cleaning of all sintering machines of the Works.
Recently, “Zaporozhstal” Steel Works implemented number of big modernization projects, among which – commissioning of renovated sinter machine №1 in complete set with hi-tech gas cleaning in 2013. In blast furnace process, Pulverized Coal Injection plant was commissioned in 2012.
In the plans – development projects on renovation of blast furnaces № 3 and № 5, construction of new turbo blower and other construction projects.